MCA Senegal 2 – Transmission Lines (2023-2025)

MCA Senegal 2 – Transmission Lines

Table of Contents

 

Figure 1 Power transmission line cable route

Before site investigation began, we audited laboratories in both Africa and Europe to ensure that best practices were in place. Where necessary, we specified improvements to testing procedures. This helped ensure that the highest quality data would be collected. During the site investigation, our client representatives were on site to carry out in-person quality control and quality assurance. This “boots on the ground” approach maintained high standards throughout. It also gave us valuable firsthand insight into the ground conditions.

Figure 3 Processed and interpreted CPT data example
Figure 4 Example alignment chart
Figure 5 Transmission line cables being deployed

FAQ

1. What was the scope of the MCA Senegal 2 transmission lines project?

The project involved laying a pair of roughly 17 km transmission cables across the Bay of Dakar, carrying power from the power plant to Senegal’s capital. The route ran mainly through a subsea trench, with land sections installed primarily using horizontal directional drilling (HDD).

2. What role did GeoIntel play in the project?

GeoIntel supported the project for two years, from the earliest planning stages through delivery of a comprehensive geotechnical interpretive report and integrated ground model, covering site investigation planning, contractor selection, laboratory management, data interpretation, and final reporting.

3. How was the site investigation planned?

Starting in 2023, all preexisting data was assessed to determine additional investigation needs. A detailed plan for boreholes and CPTs was created, along with a bill of quantities, budget estimate, and technical specifications, followed by contractor shortlisting and negotiation support.

4. How was laboratory testing quality assured?

Laboratories in both Africa and Europe were audited before site investigation began to confirm best practices were in place, with improvements specified where necessary. Client representatives were also on site during fieldwork to carry out in-person quality control and quality assurance.

5. What specialist tests were included in the laboratory program?

Beyond standard geotechnical testing, specialist tests such as chemical, rock, and thermal conductivity analyses were included, which were key considerations for transmission cable design.

6. How was the ground model developed?

Borehole logs, laboratory data, geophysical surveys, and CPT results were verified, processed, and integrated by the team in-house to build a detailed ground model, identifying geohazards such as mobile sediments, shallow bedrock, and hydrocarbon-bearing materials, and subdividing the subsurface into logical engineering units.

7. What was the outcome of the project?

The transmission cables were successfully deployed and are now ready to provide power to Senegal’s capital, with the client’s package manager commending the service and support as having added real value to the project’s success.